Building defects and statutory warranties

Six years for a major defect, two for everything else.

What this is

General information about the law in New South Wales. It is not legal advice, it does not take account of your circumstances, and no solicitor–client relationship arises from reading it.

The warranties

Section 18B of the Home Building Act 1989 (NSW) implies warranties into every contract to do residential building work: that the work will be done with due care and skill and in accordance with the plans and specifications set out in the contract, that materials will be good and suitable for the purpose, that the work will be done "in accordance with, and will comply with, this or any other law" (s 18B(1)(c)), and that the work will result in a dwelling reasonably fit for occupation.

The periods

Section 18E(1): proceedings for breach of a statutory warranty must be commenced within six years for a breach that results in a major defect, and within two years in any other case, running from the date the work was completed.

What is a major defect

Defined in s 18E(4): a defect in a major element of a building attributable to defective design, defective or faulty workmanship, defective materials, or a failure to comply with the structural performance requirements of the National Construction Code, that causes or is likely to cause the inability to inhabit or use the building for its intended purpose, the destruction of the building, or a threat of collapse. Waterproofing failures and fire safety defects commonly qualify. Cosmetic and finishing defects do not.

Section 18E(1)(e)Where a breach of warranty becomes apparent within the last six months of the warranty period, proceedings may be commenced within a further six months after the end of the warranty period — not six months after discovery. The further six months runs from the end of the warranty period, not from the date you discover the defect.

Who can sue

The warranties run with the building. A successor in title has the same rights as the original owner, so a purchaser can enforce against the builder even without a contract. In a strata scheme, the owners corporation enforces in respect of common property.

What preserves the right

  • The date of completion of the work is established first, because every period runs from it.
  • Expert evidence is obtained early. Scott Schedules require defect-by-defect particulars and costings.
  • Written notice of the defects and access to rectify are ordinarily given. Refusing reasonable access can reduce recovery.
  • Correspondence does not stop time running. File before the period expires, even if negotiations are on foot.
Current as at September 2026. Check anything here against your own documents and dates before you act on it.

If this is your situation

The strata page sets out what the work involves and what it costs, and the fee list gives the figure for every step.

Need this dealt with?

Strata — what we do, and what it costs.

See Strata

Ask the solicitor about this

If your own facts do not match the guide, write them down. Twenty minutes on the phone is at no charge, and if the answer is that you do not need a solicitor, that is what you will hear.

A mobile or an email — whichever you would rather we used.

Replied to the same business day. Sending this does not create a solicitor–client relationship — we act after a conflict check and a written engagement. If it is urgent, call 1300 992 219.

No charge

What's happened?

Describe it in your own words.

Email me this guide

As a PDF. One click unsubscribes you.

Call now — 1300 992 219
WeDo Legal assistantType anything · not legal advice
Type in your own words. fees opens the published list · send it reaches the solicitor.
General information only. Not legal advice, and no solicitor–client relationship arises until an engagement is confirmed in writing and a conflict check is completed.